# MoSCoW Prioritization: Template and Real Example

Published 2026-11-27 · Updated 2026-11-28

Canonical: https://www.trymurmur.studio/blog/moscow-prioritization-template

A MoSCoW prioritization template you can paste, the DSDM effort rule most teams skip, and a real PRD showing how Must, Should, Could and Won't landed.

Disclosure: I build Murmur, the tool that produced the real example in this piece. The template and method work without it.

Most feature lists I see aren't prioritized. They're sorted. Everything important sits at the top, everything else sits below, and when the deadline moves, nobody knows what to drop. MoSCoW fixes that if you use the whole method, including the two parts most teams skip: the effort check and the Won't list.

Below is the method as its source describes it, a template you can paste into a doc or a ticket, and a real PRD where you can see how the buckets came out.

## What MoSCoW is, and the one question that sorts it

MoSCoW splits requirements into four buckets: Must have, Should have, Could have and Won't have this time. It's part of the DSDM agile framework, and the [DSDM handbook](https://www.agilebusiness.org/wp-content/uploads/2026/05/DSDM-Agile-Project-Framework-Handbook.pdf) gives it a full chapter, "MoSCoW Prioritisation".

The handbook's test for a Must is a single question: what happens if this isn't delivered? If the honest answer is that the release is pointless, unsafe, illegal or not viable, it's a Must. If there's any workaround, even a painful manual one, it isn't. In my experience, that's a stricter bar than most teams use.

Here's how the handbook separates the rest, in my paraphrase:

| Bucket | What it means | When time runs short |
|---|---|---|
| Must have | The minimum the release commits to. DSDM reads MUST as "Minimum Usable SubseT". | Kept. If a Must is at risk, the release is at risk. |
| Should have | Important and painful to leave out, but the release still works, perhaps with a workaround. | Dropped only after the Coulds. |
| Could have | Wanted, with less impact if it's missing. | The first to go. This bucket is your contingency. |
| Won't have this time | Agreed not to be delivered in this timeframe, and written down. | Already out, on purpose. |

The difference between a Should and a Could is the degree of pain: how much value is lost, or how many people are affected, if it's missing.

## The rule most teams skip: balance on effort, not count

This is the part that makes MoSCoW work as a plan. The DSDM handbook recommends keeping Must-have effort to no more than about 60% of the total, with roughly 20% of the effort in Could-haves as a contingency pool. It treats going above 60% as risky unless your estimates are accurate, the approach is well understood, the team is performing (in the Tuckman sense) and the environment is low-risk.

![One bar split by effort: Must have up to about 60%, Should have the rest, Could have about 20% as contingency, with a marker at 60%. Won't haves are left out of the total.](https://www.trymurmur.studio/blog/moscow-prioritization-template/effort-balance.jpg)

Two things follow from that.

First, it's measured in effort, not in number of items. Nine Musts out of twenty features tells you nothing until you know how big each one is. One Must can be half the release.

Second, if everything looks like a Must, the handbook reads that as often a sign the requirements haven't been broken down far enough. "User accounts" might be a Must; "sign in with five providers" usually isn't. Split the item, then sort the pieces.

## A MoSCoW prioritization template you can paste

Copy this into a doc, a wiki page or a ticket. The effort column is what turns it from a wish list into something you can check.

```markdown
# MoSCoW: [Release or timebox name]

Timebox: [start date] to [end date]
Total estimated effort: [e.g. 40 person-days]
Must-have effort: [x] of [total] = [x]%   (aim: no more than ~60%)
Could-have effort: [y] of [total] = [y]%  (aim: ~20%, your contingency)

## Must have
| ID | Feature (what the user can do) | Effort | If it's not delivered... | Rationale |
|----|--------------------------------|--------|--------------------------|-----------|
| M1 |                                |        |                          |           |

## Should have
| ID | Feature | Effort | Workaround if it slips | Rationale |
|----|---------|--------|------------------------|-----------|
| S1 |         |        |                        |           |

## Could have
| ID | Feature | Effort | Rationale |
|----|---------|--------|-----------|
| C1 |         |        |           |

## Won't have this time
| Feature | Why not now | Revisit when |
|---------|-------------|--------------|
|         |             |              |

## Changes
- [date]: [item] moved from [bucket] to [bucket] because [reason]. Agreed by [name].
```

The "If it's not delivered..." column is the DSDM question written down. If you can't fill it with something like "we can't launch", the item belongs lower. The Changes log stops priorities from drifting silently between meetings.

## How to fill it in, step by step

1. **Fix the timebox first.** MoSCoW works best against a deadline and a team. "Won't have" means not in this timebox; it can come back in a later one.
2. **Write each feature as something a user can do.** "Export the plan as PDF" can be estimated and tested. "Better exports" can't.
3. **Ask the question for every item.** What happens if it isn't delivered? Only items with no workaround go in Must.
4. **Estimate, then check the balance.** Add up the effort per bucket. If Must is over 60%, split the large Musts or move items down until it isn't.
5. **Write the Won'ts people will actually ask for.** Adjacent features, integrations, an admin panel, a mobile app. Give each a reason. This is the list that ends the "can we just add..." conversations mid-build.
6. **Give every item a rationale.** A user quote, a research finding, a competitor gap, a deadline. "Users want it" isn't one.
7. **Revisit at each timebox.** The handbook applies priorities at several levels (the project, each increment, each timebox), so a Must for the project can be a Should or Could in an early increment, and a Must for an increment can sit lower in an early timebox.

## A real example: the Awas PRD

Awas is one of my own ideas: an AI home-design tool for families building on their own plot. I recorded a 4:37 voice memo about it and Murmur produced a PRD in a run that took 10m 37s. The PRD and the rest of the run are public at [/examples/aavaas](https://www.trymurmur.studio/examples/aavaas).

The PRD has 20 features in scope, plus 10 Won'ts, which sit outside the total as DSDM treats them:

| Bucket | Count | Examples |
|---|---|---|
| Must have | 9 | Spoken or typed plot-and-family brief; Design-changing follow-up questions only |
| Should have | 7 | Hindi interface; Decision rationale page |
| Could have | 4 | Sun study for the user's city; Dusk-lit view |
| Won't have | 10 | Studio edition for architects; Pre-designed model catalogue; Cost estimate or BoQ from the model |

A few things are worth noticing.

**The Won't list is longer than the Must list.** Ten Won'ts against nine Musts. That's the list that keeps scope steady once building starts.

**Some Won'ts go against the market on purpose.** Murmur's competitor research for Awas listed a cost or budget indication among its table stakes. The PRD still put a cost estimate in Won't have. A table stake you choose not to match belongs in the Won't list with a reason, so it's a decision rather than an oversight. The [competitive analysis template](https://www.trymurmur.studio/templates/competitive-analysis) walks through the same example.

**Rationales point at evidence.** The catalogue Won't, for example, cites the research: a competitor sells a large catalogue of ready-made designs, and Awas starts from the user's own plot and family instead.

**The buckets decided what reached the board.** In the same run, the nine Musts and seven Shoulds became epics (17 in all, counting one for engineering) with 64 stories. The Coulds and Won'ts stayed in the PRD as scope.

What this example doesn't show is the effort check. The counts above are counts, not estimates. 9 Musts out of 20 features in scope is 45% by count, but the DSDM rule is about effort, and you'd need your own estimates to know whether this release passes it. I'd treat any generated MoSCoW list, Murmur's included, as a first draft for that conversation, not the end of it.

## Why the Won't list matters even more with a coding agent

If you build with Claude Code or Cursor, MoSCoW does a second job. A single prompt has no edges. From one prompt, an agent usually can't tell a Must from a nice-to-have, and unless something tells it what not to build, it has to guess. Hand it a prioritized list instead: the Musts as the build order, the Won'ts as an explicit "don't build these" list. The agent then starts from a plan rather than from a guess. I wrote more about structuring a PRD for agents in [How to Write a PRD for Claude Code and Cursor](https://www.trymurmur.studio/blog/write-a-prd-for-claude-code-and-cursor).

That's the problem Murmur is built for. You say or type your idea, and it does the groundwork: competitor research, a PRD with MoSCoW features, usually with a rationale for each, a tech design, a brand kit, a roadmap and a board of epics and stories. You download the files as Markdown or pull them into your repo through the [MCP server](https://www.trymurmur.studio/mcp); Jira and Confluence are optional, if you choose them for a run. Its limits: you record a voice memo on your phone or desktop, or type the idea in the desktop app or send it as text through the MCP server; a run with Jira and Confluence creates a new project and space in your own Atlassian site rather than working in ones you already have; and it doesn't export to Linear, Notion or GitHub. The first idea is free; after that it's $7 per idea or a monthly plan.

If you already have a MoSCoW list in Markdown, the free [PRD to Jira CSV converter](https://www.trymurmur.studio/tools/prd-to-jira-csv) reads Must/Should/Could/Won't headings and maps them to Jira priorities and labels, leaving Won'ts out unless you include them. The [PRD template](https://www.trymurmur.studio/templates/prd) has a MoSCoW section with a description and a rationale for each feature, and the [user story template](https://www.trymurmur.studio/templates/user-story) covers the next step down.

## When MoSCoW is the wrong tool

MoSCoW works best with a fixed deadline and a scope you're negotiating. It's weaker at ranking a long backlog against itself: inside one bucket, everything is equal.

For that, a scoring model can help. RICE, which Sean McBride described on [Intercom's blog](https://www.intercom.com/blog/rice-simple-prioritization-for-product-managers/), scores each idea on Reach, Impact, Confidence and Effort, so you're comparing "total impact per time worked" across ideas. It's useful for choosing between twenty growth ideas; it says less about what a release can't ship without. You can also use both: RICE to choose what goes into the next timebox, MoSCoW to protect the timebox once it starts.

Whichever you use, write down the Won'ts. It's the cheapest section to write, and in my experience it settles more arguments than any other.

## Sources

- DSDM recommends typically no more than 60% Must Have effort, and a pool of Could Haves of typically around 20% of the total effort: https://www.agilebusiness.org/wp-content/uploads/2026/05/DSDM-Agile-Project-Framework-Handbook.pdf
- Awas: a 4:37 memo, a 10m 37s run, 17 epics and 64 stories: https://www.trymurmur.studio/llms.txt
- The Awas PRD has 20 features in scope, Must have (9), Should have (7) and Could have (4), plus 10 Won't haves: https://www.trymurmur.studio/examples/aavaas
- 9 of the Awas PRD's 20 features are Must have: 9 / 20 = 45% by count (worked out from the page's counts): https://www.trymurmur.studio/examples/aavaas
- First idea free; $7 per idea after that, or a monthly plan: https://www.trymurmur.studio/llms.txt

Facts checked 2026-11-27